Project Server 2010

Knowledge based articles regarding Project Server 2010

Team Members cannot see their assigned tasks on the Timesheet page or Task page in PWA
Description A project manager adds enterprise resources to the project team using the Build Team dialog in Project Server, and then assigns these ent...
Tue, 23 Sep, 2014 at 5:57 AM
Resolve Corruption in the Local Cache
Background Information Whenever you save an enterprise project to the Project Server database, Project Professional 2007 or 2010 saves a copy of your proj...
Wed, 27 Nov, 2013 at 10:48 AM
Duplicate view or table error when opening an enterprise project
Background Information This problem occurs when the Project Server Administrator applies or copies the Gantt Chart view or any other non-enterprise view ...
Thu, 28 Nov, 2013 at 10:42 AM
Cannot enter Physical Percent complete at the Summary Task level
Background Description You cannot enter Physical Percent Complete into summary tasks. Resolution This behavior is by design.  Physical % ...
Thu, 28 Nov, 2013 at 11:09 AM
Clearing unprocessed timesheets for an inactive user in Project Server 2010
Background Description When a resource leaves your company, you should always make sure that all timesheets for the resource are processed before making t...
Wed, 27 Aug, 2014 at 1:00 PM
Load Summary Resource Assignments checkbox is disabled in the Login dialog
Background Information When a user launches Microsoft Project Professional, the "Show Summary Resource Assignments" checkbox is disabled (gray...
Thu, 28 Nov, 2013 at 11:13 AM
Where to find actual overtime work and planned overtime work in OLAP cube project server 2010
Background Description When you build an OLAP cube in Project Server 2007 or 2010, the system builds 14 separate cubes. Finding timesheet informa...
Thu, 28 Nov, 2013 at 11:16 AM